Own land availability.
You must own the land plot on which you plan to build a house

1
DAY

Sign the contract

Decide what you want
What kind of house project do you want? How many bedrooms and how many square meters would you like? Where would you like to build? (Most module builders serve only serve a specific area)

2
DAY

Start planning, designing

Once you have decided with a builder, the next step is to choose which of their plans you would like. Check out our look at some modular floor plans. Each manufacturer has unique plans, but they should have a good understanding of what your home might look like

Please keep in mind (!): 

You need to obtain permission from the local municipal building authority of the house architectural project.  This process will take about 3-6 months, depending on the area in which you own the land.

3
DAY

Assembled house is prepared for transportation

21
DAY

Assembled and prepared for transportation

23
DAY

We start assembling Your house

30
DAY

Indoor works